How to forecast cost to complete by cost code on a custom home
A monthly, line-by-line process that turns field knowledge into a projected finish you can trust.
Short answer: Cost to complete is what is left to spend on each cost code to finish the house. Build it bottom up each month: the unbilled part of signed subcontracts and purchase orders, plus a fresh estimate for work not yet bought, plus known changes and risks. Cost to date plus cost to complete is the projected final cost.
How do you forecast cost to complete for a custom home?
For each cost code, estimate what remains to be spent, not what remains in the budget. Use the unbilled part of signed subcontracts and purchase orders, fresh pricing for work not yet bought, and known changes. Cost to date plus cost to complete is the projected final cost, compared with the revised budget.
| Cost code status | How to estimate cost to complete | Made-up example |
|---|---|---|
| Fully committed sub | Contract value plus approved changes minus billed to date | $42,000 + $2,000 - $30,000 = $14,000 |
| Partly bought | Unbilled committed amount plus a fresh estimate for what is not bought | $9,000 committed + $6,500 estimate = $15,500 |
| Not yet bought | Current quote, or the allowance updated for selections | $18,000 quote |
| Time-based, such as supervision | Monthly cost times months remaining | $6,500 x 3 = $19,500 |
Made-up numbers for illustration.
Where this fits
Our guide on how to read a job cost report explains the columns and how to judge variance. This guide is about producing the one column software cannot fill in on its own: cost to complete. Without an honest number there, projected finish, projected margin and percent complete on the WIP schedule are all guesses. It builds on our pillar guide, how to job cost a custom home.
The formula
Construction finance writers describe the same core equation in different words. Jet.Build puts it this way: projected final cost equals actual cost to date, plus remaining committed cost, plus forecast remaining uncommitted cost, plus expected change or risk exposure. Two terms get mixed up a lot:
- Cost to complete (also called estimate to complete) is the remaining spend from today to the finish.
- Projected final cost (also called estimate at completion) is cost to date plus cost to complete.
Variance at completion is the revised budget minus projected final cost. That is the number the owner acts on.
Want a cost to complete forecast on every active house? Request a Relationship Assessment.
Four ways to estimate it
- Bottom up, by cost code. Walk each code with the project manager and estimate what is left from current quotes, signed contracts and remaining scope. Planyard calls this the most accurate method and Jet.Build calls it the most defensible. It takes the most time, which is why it is done monthly.
- Top down, from percent complete. Budget times the share of work not done. Quick, but it averages away problems. A house can be 60% complete overall while one trade runs at double its budget.
- Trend. Project the rest of the job from how it has run so far. Useful as a check: if framing ran 10% over, ask why the rest of the framing forecast says on budget.
- Earned value. Common on large projects with formal controls. For most owner-led home builders it is more structure than the job needs.
The hh2 glossary also lists parametric (cost per square foot or per unit from history) and analogous (a similar past house, adjusted) estimates. Both are handy for codes you have not bought yet.
Know what your software assumes
Job management software fills in a default so the column is never blank. Buildertrend documents that projected cost on each code is the greatest of revised budget plus builder variance, committed cost, or actual cost, unless you pick another projection reference or enter an adjustment. Cost to complete is projected minus actual. Marking a code complete resets projected cost to actual. That conservative default is a good floor, but it cannot know about the extra you agreed to on site yesterday or the trade that still has not been bought. Treat the default as the starting point for the monthly review, not the answer.
The monthly process, code by code
- Close the books first. Enter every bill for the month and accrue work done but not billed, so cost to date is real. See the month-end close checklist.
- Update commitments. Add new purchase orders and subcontracts, reduce them as bills come in, and close them when the work is done. See purchase orders and committed costs.
- Sort each open code into one of four states.
- Done: cost to complete is zero. Mark it complete so it stops carrying budget.
- Bought out: the unbilled part of the contract, plus any extras you already know about.
- Partly bought: the unbilled commitment plus an estimate for the rest of the scope.
- Not bought: a fresh estimate from current quotes, not the original budget by default.
- Check allowances and selections. If the client picked over the allowance, the cost goes up and so should the contract through a change order. See allowance tracking.
- Decide what is left in contingency. Move known risks into the codes they hit and keep the rest visible. See contingency tracking.
- Add it up and explain the big moves. For any code whose projected finish moved more than an amount you set, write one line on why. That note is what makes next month faster.
A SAMPLE forecast (made-up numbers)
SAMPLE only. Four codes on one custom home at month end:
- Framing labor: revised budget $62,000, cost to date $58,500, complete. Cost to complete $0. Projected $58,500, $3,500 under.
- Electrical: budget and subcontract $41,000, billed $24,600, plus a $2,200 extra for added circuits agreed on site. Cost to complete $18,600 ($16,400 unbilled plus the extra). Projected $43,200, $2,200 over. If the client asked for the circuits, the extra should become a change order.
- Cabinets: not bought. Original budget $38,000, current quote $44,500. Cost to complete $44,500, $6,500 over.
- Flooring allowance: $18,000 allowance, client selection $23,000. Cost to complete $23,000. The $5,000 overage goes to the client by change order, so the revised budget and contract both rise.
A budget-minus-actual autopilot would have shown cabinets on budget and electrical with $16,400 left. The bottom-up review finds $8,700 of overrun on electrical and cabinets, less $3,500 saved on framing, plus a $5,000 allowance overage to bill, while there is still time to act.
Common mistakes
- Using budget minus actual as the forecast every month.
- Counting a bill against both actual cost and an open purchase order, which double counts the same dollars.
- Leaving finished codes open, so leftover budget looks like savings that never come.
- Not updating the forecast after a change order is approved.
- Letting the forecast live in one person's head instead of in the report.
Why it matters beyond the job
On a WIP schedule, cost-to-cost percent complete is cost to date divided by projected final cost. A low cost to complete inflates percent complete, earned revenue and earned profit. See what is a WIP schedule. On a spec home, the same forecast drives projected margin at sale, and on a loan it shows whether the remaining draw budget will cover the finish. See lender draw budget vs job budget.
How we help
Your project manager knows the field. Our team turns that into a monthly cost to complete by house and cost code, ties it to the books in QuickBooks Online and Buildertrend or JobTread, and flags the codes that moved. Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, fractional controller, pricing or request a Relationship Assessment.
Sources
- Jet.Build, Construction cost forecasting: methods, EAC and cost-to-complete
- Planyard, Cost-to-complete forecasting in construction
- hh2, What is cost to complete (CTC) in construction?
- Buildertrend, Job Costing Budget overview
- Buildertrend, Job Costing Budget columns (Client Portal FAQs)
Common questions
What is cost to complete in construction?
The remaining cost to finish the work from today. Added to cost to date, it gives the projected final cost of the house or cost code.
How do you calculate cost to complete?
By cost code: the unbilled part of signed subcontracts and purchase orders, plus an estimate for work not yet bought, plus known changes and risks.
Is budget minus actual a good cost to complete?
Only as a quick check. It assumes the rest of the job will run exactly to budget, which hides overruns that are already known in the field.
How often should builders update cost to complete?
Monthly, right after the books close, and again whenever a large change order or buyout happens.
What does Buildertrend use as projected cost by default?
Buildertrend documents the greatest of revised budget plus builder variance, committed cost or actual cost, unless you choose another projection reference or adjust it.
Can you prepare our monthly cost to complete?
Yes. Our team prepares it by house and cost code with your project manager's input and ties it to your books each month.
How do you forecast cost to complete for a custom home?
For each cost code, estimate what remains to be spent, not what remains in the budget. Use the unbilled part of signed subcontracts and purchase orders, fresh pricing for work not yet bought, and known changes. Cost to date plus cost to complete is the projected final cost, compared with the revised budget.
Related
- How to read a job cost report
- How to job cost a custom home
- Purchase orders and committed costs
- What is a WIP schedule
- Job costing service
- Glossary: Budget vs actual
- Glossary: Committed cost
- Glossary: Cost to complete
- Request a Relationship Assessment
- House margin and markup calculator
- Original vs revised budget vs forecast
By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.