Budget vs actual: definition and example
A plain definition for custom and spec home builders, with a worked example.
Definition: Budget vs actual is a comparison of what a builder planned to spend on each cost code of a house against what has actually been spent. The difference is the variance. Reviewed monthly, it shows overruns early enough to change course, reprice a change or hold an allowance.
How it works for a home builder
The report is only as good as its inputs. The budget needs to be loaded by cost code before the first bill is paid, and every actual cost needs the same house and code. A budget vs actual that mixes committed and paid costs, or ignores unbilled changes, will mislead.
Useful versions show budget, actual to date, committed but unpaid, and a forecast to finish. Variance on actual to date alone can look fine early in a job and bad later, because most costs have not hit yet.
Example
Lot 14 at 60% of expected cost. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Electrical budget | $46,000 |
| Actual to date | $31,500 |
| Committed, not yet billed | $9,800 |
| Forecast at finish | $48,700, $2,700 over |
Made-up figures. Actual alone (31,500 vs 46,000) looks 14,500 under. Adding commitments shows a $2,700 overrun is coming.
Common questions
What is a variance in budget vs actual?
The dollar or percent difference between the budgeted cost and the actual cost for a cost code. Over budget is usually a positive variance on cost.
How often should a builder review budget vs actual?
Monthly at minimum, and weekly on large or fast-moving houses. The point is to catch overruns while they can still be changed.
Why does my budget vs actual look fine and the house still loses money?
Common causes are unbilled change orders, uncommitted costs not forecast, miscoded costs and a stale budget. See the guide on reading a job cost report.
Sources
- Procore, Construction cost reporting
- Buildertrend, Job Costing Budget overview
- Built, Construction job cost report: what it reveals
Related guides
- How to read a job cost report
- Monthly job cost reports for builders
- Forecasting cost to complete by cost code
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.