Purchase orders and committed costs in QuickBooks Online

See what each house already owes before the bills arrive.

Short answer: A purchase order records a cost you have committed to but not been billed for yet. In QuickBooks Online Plus or Advanced, enter each PO by house and cost code, add it to the vendor bill when it arrives, and run Open Purchase Order Detail by project to see committed cost on every house.

Why committed cost matters

A job cost report that shows only posted bills looks backward. If you signed a $40,000 framing subcontract and have been billed $15,000, the house has $25,000 of cost coming that no posted transaction shows. Committed cost is that open amount. Add it to actual cost to date and the honest cost to complete, and you get a projected finish you can trust. Our guide on how to read a job cost report walks through those columns. This guide covers how to capture commitments in QuickBooks Online and in your project software.

What a QuickBooks Online purchase order does (and does not do)

  • Plan. Intuit says purchase orders are only available in QuickBooks Online Plus and Advanced.
  • No posting. A PO is an order, not an expense. It does not change your Profit and Loss or balance sheet. The bill, check or expense that you link to it does the accounting.
  • Linking. When you enter a bill for a vendor with open POs, QuickBooks offers them in a side panel. Select Add and the PO lines fill in. You can add part of a PO, and you can link several bills to one PO.
  • Closing. QuickBooks closes a PO automatically once all of its quantities have been added to bills, checks or expenses. If you delete the link later, the PO stays closed until you reopen it by hand.
  • Reports. Open Purchase Order List and Open Purchase Order Detail sit under Reports, Expenses and vendors. Detail shows what is still open and what has been received.

Want commitments visible before the bills arrive? Request a Relationship Assessment.

Setup for job costing

  1. In Account and settings, Expenses, turn on purchase orders, the items table on expense and purchase forms, tracking expenses and items by customer, and billable expenses if you bill cost-plus work.
  2. Use your products and services as cost codes, the same list your estimate and project software use. See cost codes for custom home builders.
  3. On every PO line, pick the cost code item and the customer or project for the house. A PO with no project gives you a commitment you cannot see by house.
  4. Enter a PO for every signed subcontract and every large material order, for the full agreed amount. Name it with the house and trade so the vendor and your team can find it.
  5. When a sub change order is approved, update the PO amount the same day so committed cost matches what you owe.

Bills against POs

  • Always start the bill from the vendor and Add the open PO. Typing a new bill from scratch leaves the PO open and double counts the commitment.
  • For progress billing, adjust each line to the amount billed this period. The remaining amount stays open as committed cost.
  • When a sub finishes under the PO amount, close the PO by hand so the leftover does not sit as phantom commitment.
  • Retainage held on a sub belongs in retainage payable, not as an open PO balance. See retainage and customer deposits.

If you run POs in Buildertrend or JobTread

Most builders on project software issue POs there, not in QuickBooks. That is fine, as long as one system owns POs and one path creates bills.

  • Buildertrend. Approved POs count as committed costs in the Job Costing Budget, and unapproved POs show as pending. Buildertrend POs do not sync to QuickBooks Online; bills do. Create the bill from the PO in Buildertrend and send it to QuickBooks. If a bill is entered straight into QuickBooks instead, Buildertrend lets you mark that cost as Actual Cost from a Commitment so it is not counted twice in projected cost. It may still not reduce the open amount on the specific PO, so check the PO balance by hand.
  • JobTread. JobTread lists vendor bills, expenses, cost codes and jobs among the records its QuickBooks Online integration syncs. Purchase orders are not on that list. Turn each PO into a vendor bill in JobTread so the cost code and job carry into QuickBooks.
  • Either way, do not also enter the same commitments as QuickBooks POs. Two PO lists will never agree.

Our Buildertrend and QuickBooks Online guide covers job mapping and the monthly tie-out between the two systems.

Monthly commitments review

  1. Run Open Purchase Order Detail (or the open PO report in your project software) by house.
  2. Close any PO where the work is done and the final bill is in.
  3. Ask the project manager about any PO with no bill in 60 days or more. Is the work late, or was it never done?
  4. Carry the open PO total per house into the committed column of your job cost review.

SAMPLE (made-up numbers)

SAMPLE only. A builder issues a $40,000 framing PO on House 12, cost code 3000 Framing. The sub bills $15,000 at walls and $15,000 at roof, each added from the PO. Open PO balance: $10,000. The framing budget is $42,000. Actual is $30,000, committed is $10,000, and the project manager says cost to complete beyond the PO is $1,500 for blocking. Projected finish is $41,500, $500 under budget. Without the PO, the same report would show $12,000 left in the budget and look $11,500 safer than it is. This SAMPLE is not a market claim.

How we help

Each month our team codes every bill to the house and cost code, ties open commitments to the job cost report, and makes sure QuickBooks and Buildertrend or JobTread agree. Our founder reviews every close. Builder Books is our core monthly job-cost service. Builder Controller adds WIP and the 13-week cash forecast. Start with a $1,500 Margin Review for written findings. See pricing, job costing, QuickBooks and Buildertrend or JobTread cleanup or request a Relationship Assessment.

Sources

Common questions

Which QuickBooks Online plans have purchase orders?

Intuit says purchase orders are only in QuickBooks Online Plus and Advanced. Simple Start and Essentials do not have them.

Do purchase orders show on my job profit reports?

No. A PO does not post, so it does not appear on Profit and Loss by project. Run Open Purchase Order Detail by customer or project and add it to your job cost review.

Why is a PO still open after the sub was paid?

Usually the bill was typed in without adding the PO, so QuickBooks does not know they match. Link the bill to the PO, or close the PO by hand.

Should I enter POs in QuickBooks if I use Buildertrend?

Usually not. Issue POs in Buildertrend, create bills from them there, and sync the bills. Two PO lists in two systems never agree.

Is a signed subcontract a purchase order?

For job costing, treat it as one. Enter the full subcontract amount as a commitment by house and cost code, and update it when a sub change order is approved.

Related

By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.