Cost to complete: definition and example
A plain definition for custom and spec home builders, with a worked example.
Definition: Cost to complete is the estimated amount still needed to finish a house, by cost code. Added to the cost already spent, it gives the estimated total cost at finish. A builder uses it for forecasting margin, calculating percent complete on a WIP schedule and planning draws and cash.
How it works for a home builder
Cost to complete is a forecast, not a bookkeeping entry, so it should be set by the person who knows the work, usually the project manager, and reviewed monthly. Plugging in the remaining budget is quick but wrong whenever a trade is trending over.
Estimated total cost equals cost to date plus cost to complete. That total is the denominator in the cost-to-cost percent complete used on a WIP schedule, so a careless cost to complete flows into earned revenue.
Example
Lot 14 forecast. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Cost to date | $250,000 |
| Cost to complete (PM estimate) | $200,000 |
| Estimated total cost | $450,000 |
| Percent complete (cost to cost) | 55.6% |
Made-up numbers. 250,000 divided by 450,000 is 55.6%.
Common questions
Who should set cost to complete?
The project manager or superintendent, reviewed by the owner and bookkeeper. Do not plug it from the original budget.
How is cost to complete different from remaining budget?
Remaining budget is budget minus actual. Cost to complete is your current best estimate of what is left, which may be higher or lower.
How often should cost to complete be updated?
Monthly, before the WIP schedule is prepared.
Sources
- hh2, What is cost to complete in construction
- Planyard, Cost-to-complete forecasting in construction
- CFMA, WIP accounting: critical and often misunderstood
Related guides
- Forecasting cost to complete by cost code
- What is a WIP schedule?
- Monthly WIP review meeting for builders
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.