Cost-to-cost method: definition and example
A plain definition for custom and spec home builders, with a worked example.
Definition: The cost-to-cost method measures how complete a house is by dividing the cost incurred to date by the estimated total cost of the house. The resulting percent complete is multiplied by the contract price to compute earned revenue. It is the most common input method on a builder's WIP schedule.
Also called: cost-to-cost percent complete
How it works for a home builder
It is popular because both numbers are already in the books and the estimate. Its weakness is that cost incurred does not always equal work done. Materials bought early and stored uninstalled raise the percentage before the work happens, which overstates progress.
Many builders adjust by excluding uninstalled materials or using a different measure for large early purchases. Whatever you choose, apply it the same way each month.
Example
Effect of uninstalled materials. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Cost to date | $250,000, including $30,000 of uninstalled windows |
| Estimated total cost | $450,000 |
| Percent complete as booked | 55.6% |
| Percent complete excluding uninstalled windows | 48.9% |
Made-up numbers. 220,000 divided by 450,000 is 48.9%.
Common questions
Why is cost to cost used so often?
It uses figures builders already track, so it is simple to apply monthly.
What goes wrong with cost to cost?
Early material purchases and stale estimates distort percent complete.
Are there other ways to measure percent complete?
Yes, such as milestones, inspections or units delivered. A builder should choose a method and apply it consistently.
Sources
- Modus Alliance, Percentage-of-completion accounting for contractors
- 26 CFR 1.460-3, long-term construction contracts (Cornell LII)
- CFMA, WIP accounting: critical and often misunderstood
Related guides
- Uninstalled materials and percent complete
- Percentage of completion vs completed contract
- Forecasting cost to complete by cost code
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.