Guide

The monthly WIP review meeting for home builders

A 30-minute agenda for owner-led builders: who attends, what to prepare and the questions to ask on every open house.

Short answer: A monthly WIP review is a short meeting where the owner, the person who keeps the books and the project managers go through every open house and answer two questions: what will this house cost in total, and what will the final contract amount be? For most owner-led builders, 30 minutes with a one-page pre-read per house is enough.

Why a meeting, and not just the report

A WIP schedule is only as good as the estimates in it. Cost to date and billed to date come from the books. The estimated total cost, and so percent complete, earned revenue and over or under billing, come from the people running the houses. If nobody asks them each month, the estimate is just last month's number carried forward.

Sage's guidance on the monthly WIP and forecasting meeting puts it simply: every job has to answer two questions, the total projected cost and the anticipated final contract amount, and the difference is the forecasted profit. It also calls the meeting a forcing event for project managers juggling many priorities. Accounting firm JMCO recommends holding the review monthly, as a standing part of the close, not once a quarter or only at year end.

Who attends

  • The owner. Makes the calls: pricing, schedule, staffing, how to handle a dispute.
  • The person who keeps the books (bookkeeper, controller or outside firm). Brings the numbers and runs the meeting.
  • Project managers or superintendents for each open house. They own the cost to complete.
  • Your CPA, now and then. JMCO suggests bringing in the outside CPA near year end or during big changes.

Keep the group small. Sage notes that these meetings are often kept to a small number of essential people.

Want a WIP review you can run in 30 minutes? Request a Relationship Assessment.

The pre-read: one page per house

Send it two or three days before the meeting, after the month's bills are entered. For each open house:

  • Contract amount and approved change orders to date.
  • Cost to date by major cost code, from the job cost report.
  • Last month's estimated total cost and the resulting percent complete.
  • Billed to date and the current over or under billing. See over and under billing.
  • Pending change orders, open allowances and contingency left.
  • Receivables and retainage outstanding.

A 30-minute agenda

  1. Tie-out, 3 minutes. The bookkeeper confirms the WIP totals tie to the books: contract revenue, cost and billings. Kruse and Crawford CPAs open their monthly WIP agenda by reconciling contract value, cost and billing to the books.
  2. House by house, about 4 minutes each. Same questions, same order, every month (below).
  3. Cash and billing, 4 minutes. What can be billed or drawn this month that has not been. What is overdue. See 13-week cash forecast.
  4. Decisions and owners, 3 minutes. Read back each action, who owns it and when it is due.

With five or six open houses, that fits in half an hour. With more, split by project manager or run two short meetings.

The questions for every house

  • Schedule: where is the house against plan, and what is slipping?
  • Cost to complete: what is left to do and what will it really cost on the big lines? Not the remaining budget, a fresh number. See forecasting cost to complete by cost code.
  • Change orders: what is approved, what is pending, and what work was done without a signed change? See change order tracking.
  • Margin trend: is projected profit holding, fading or gaining since last month and since the contract, and why? Sage lists profit fade or gain as a standing item.
  • Over or under billing: did the position change, and does it make sense? Large over billing can mean cash was spent ahead of the work. Large under billing can mean work done but not billed.
  • Big deliveries: are there delivered but uninstalled packages pushing up percent complete? See uninstalled materials and percent complete.

After the meeting

  1. Update the estimated total cost for each house in the WIP schedule with the numbers agreed in the room.
  2. Record the month-end over and under billing entries from the updated schedule, as your CPA has set them up.
  3. Send the action list the same day.
  4. Keep a short note for any estimate that moved a lot, with the reason. JMCO advises documenting the reasoning behind significant variances, and it is what a lender or CPA will ask about later.

Common mistakes

  • Holding the meeting before the month's bills are entered, so cost to date is wrong.
  • Accepting "on budget" without a fresh cost to complete.
  • Changing a project manager's estimate without telling them why. Sage warns this teaches people to stop doing the work.
  • Letting it become a report-out with no decisions.

How we help

Our team closes the books, builds the WIP schedule and one-page pre-read for each open house, and can run the monthly house-by-house review with you and your project managers, then posts the results. Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See WIP schedules, fractional controller, month-end close checklist, pricing or request a Relationship Assessment.

Sources

Common questions

What is a WIP review meeting?

A monthly meeting where the owner, the person who keeps the books and the project managers review every open job's estimated total cost, final contract amount and billing position, and decide what to do about jobs that moved.

Who should attend a WIP meeting at a small builder?

The owner, the bookkeeper or controller and the project managers or superintendents. Bring in your CPA near year end or during a big change.

How long should a WIP meeting take?

For an owner-led builder with five or six open houses, about 30 minutes with a one-page pre-read per house.

When should the WIP meeting happen?

Each month after the month's bills and labor are entered, and before the month-end over and under billing entries are final.

What is the most important number in the meeting?

The fresh estimate of total cost for each house. It drives percent complete, earned revenue, over or under billing and projected profit.

Can you run our WIP meeting?

Yes. Our team prepares the WIP schedule and pre-read and can run the monthly house-by-house review with you and your project managers.

Related

By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.