Guide

Cost-plus open-book reporting to your client

What to send a cost-plus client each month, how the fee is figured, and how to keep it tied to QuickBooks Online.

Short answer: On a cost-plus custom home, the client pays your actual cost of the work plus an agreed fee, so the monthly invoice has to be backed by an open-book package: a cost report by cost code, the vendor bills and labor behind it, the fee calculation, change orders and the forecast to finish. Every number should tie to QuickBooks Online.

How do you do open-book reporting on a cost-plus custom home?

Code every cost to the house and cost code as it occurs, then send the client an open-book package with each invoice: costs by cost code against the estimate, the vendor bills and labor behind them, the fee calculation, change orders and the forecast to finish. Every figure should tie to QuickBooks Online.

Package itemWhat it showsTies to
Cost report by cost codeEstimate, approved changes, actual cost, forecast and varianceJob cost report
BackupVendor bills, receipts and timesheetsBills and expenses in QuickBooks Online
Fee calculationThe fee on cost, as the contract defines itContract fee section
Change ordersSigned changes and their effect on the estimateChange order log
Forecast to finishCost to complete by cost codeMonthly forecast

Why open-book reporting is its own job

On a fixed-price house, job costing protects your margin. On a cost-plus house, job costing is the invoice. The client is paying for the cost of the work plus your fee, so every dollar you bill has to trace back to a real bill, a real labor hour or a real allowance, and the client is allowed to ask to see it. Our cost-plus vs fixed-price guide covers the basic difference. This guide is about the monthly package itself.

Standard contract forms show how much is expected. AIA Document A102 and A103, the cost-plus agreements published by the American Institute of Architects, require the contractor to keep full and detailed records of the cost of the work, give the owner and the owner's auditors access to job cost reports, invoices, subcontracts and purchase orders, and keep those records for three years after final payment. A residential contract may be shorter, but clients and their lenders often expect the same level of support. What your own contract says is a question for your attorney.

What goes in the monthly open-book package

  1. Cover summary. Contract basis, fee terms, cost to date, fee to date, billed to date, paid to date and the balance due on this invoice.
  2. Cost report by cost code. Budget (or control estimate), cost this month, cost to date and the forecast to finish for each code. This is the same layout as a good job cost report.
  3. Transaction detail. Every vendor bill, subcontractor invoice and labor charge included this month, with vendor, date, cost code and amount.
  4. Backup. Copies of the bills and invoices, and lien waivers for amounts already paid. See lien waivers.
  5. Fee calculation. Show the base the fee is applied to and the math, so the client can check it in a minute.
  6. Change orders and allowances. Approved changes, pending changes and allowance usage against each allowance. See allowance tracking and change order tracking.
  7. Forecast to complete. Where the total cost of the house is heading. On a contract with a guaranteed maximum price, this is the number the client watches most.

Want open-book reports you can send your client with confidence? Request a Relationship Assessment.

How the fee is figured

The AIA cost-plus forms let the parties set the fee as a fixed amount, a percentage of the cost of the work or another method, and residential contracts vary the same way. Whatever the method, write down three things before the first invoice: which costs carry the fee, whether your own labor and general conditions are part of the cost of the work or covered by the fee, and how the fee is treated on change orders. Most disputes we see on cost-plus jobs start with one of those three not being clear in the books.

A SAMPLE invoice, made-up numbers: cost of the work this month is $84,000, the fee is 15% of cost, so the fee is $12,600 and the invoice is $96,600 before any retainage. The package shows the $84,000 by cost code, the bills that make it up and the fee line. If the fee were a fixed $90,000 spread over the build, the package would instead show the fee earned to date under the schedule your contract sets.

Keep markup and margin straight when you talk about the fee. A 15% markup on cost is not a 15% margin. See markup vs margin.

Setting it up in QuickBooks Online and your job software

  • Code every cost to the house and cost code when the bill is entered, not at invoice time. A bill coded to the wrong job is a billing error on a cost-plus house, not just a reporting error.
  • QuickBooks Online billable expenses. Intuit's help pages describe how to mark a bill, expense or check as billable to a customer with a markup rate, then add it to the customer's invoice. That works for smaller jobs. Many builders bill from their job software instead.
  • Buildertrend open book jobs. Buildertrend documents an Open Book contract type where the invoice can pull in uninvoiced bills, approved time clock shifts and QuickBooks costs, with markup filled from the estimate by cost code and cost type. If you bill from Buildertrend or JobTread, the books still have to tie out to the same costs. See our tie-out guide.
  • Track what has been billed. Each cost should be billed once. A monthly check of cost to date against cost billed to date by house catches both missed and double-billed costs.

Monthly checklist before the invoice goes out

  1. Cost to date in the package equals the job cost report in QuickBooks Online for that house.
  2. No costs from another house, overhead or the owner's personal spending are in the detail.
  3. Credits, returns and vendor discounts are passed through as your contract requires.
  4. The fee math matches the contract terms on this month's base.
  5. Change orders are only billed once they are approved in writing.
  6. Prior payments and retainage match what the client actually paid. See retainage and customer deposits.
  7. The forecast to complete has been updated with the project manager, not copied from last month. See cost to complete by cost code.

Common mistakes on cost-plus houses

  • Billing estimates or purchase orders as if they were actual cost.
  • Keeping a vendor rebate or credit that the contract says belongs to the client.
  • Charging the fee twice on the same cost after a change order.
  • Sending a package that does not match the books, which turns one question into an audit.
  • Letting backup pile up until the end of the job, when the client's final accounting review starts.

How we help

Our team codes every cost by house and cost code, ties your Buildertrend or JobTread costs to QuickBooks Online and prepares the monthly open-book package and fee calculation for your review before it goes to the client. Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, construction bookkeeping, how to job cost a custom home, pricing or request a Relationship Assessment.

Sources

Common questions

What is open-book reporting on a cost-plus home?

A monthly package that shows the client the actual cost of the work by cost code, the bills and labor behind it, the fee calculation, change orders and the forecast to finish, all tied to your books.

What records should a cost-plus builder keep?

Bills, subcontractor invoices, purchase orders, labor records, change orders, lien waivers and job cost reports by house. The AIA cost-plus forms require these to be kept for three years after final payment. Your contract and attorney set your exact terms.

How is the builder fee calculated on a cost-plus contract?

It depends on the contract. Common methods are a percentage of the cost of the work or a fixed fee. The package should show the base and the math every month.

Can QuickBooks Online handle cost-plus billing?

Yes for many builders. It can mark costs as billable to a customer with a markup and add them to an invoice. Many builders bill from Buildertrend or JobTread, and the books must still tie out.

Is a 15% fee the same as a 15% margin?

No. A 15% markup on cost is about a 13% margin on the price. Use the term your contract uses.

Can you prepare our monthly cost-plus package?

Yes. Our team prepares the package and fee calculation by house for your review before it goes to the client.

How do you do open-book reporting on a cost-plus custom home?

Code every cost to the house and cost code as it occurs, then send the client an open-book package with each invoice: costs by cost code against the estimate, the vendor bills and labor behind them, the fee calculation, change orders and the forecast to finish. Every figure should tie to QuickBooks Online.

Related

By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.