Contingency: definition and example
A plain definition for custom and spec home builders, with a worked example.
Definition: A contingency is an amount set aside in a construction budget for unknown or unforeseen costs, usually a percent of the budget. It is spent only if surprises occur. Tracking draws against contingency shows how much cushion remains and whether the budget can absorb what is left.
How it works for a home builder
A contingency is not extra profit and it is not an allowance. It is a reserve. Each use should be logged with the reason, the cost code it moved to and the remaining balance.
Contracts differ on who owns unspent contingency. On cost-plus jobs with a guaranteed maximum price, the AIA forms address how contingency is used and shared, so read your contract.
Example
Contingency on a $432,000 budget. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Contingency, 3% of budget | $12,960 |
| Used: rock at the foundation | $5,200 |
| Used: electrical rework | $2,100 |
| Remaining | $5,660 |
Made-up numbers. 12,960 minus 7,300 equals 5,660.
Common questions
How much contingency should a builder carry?
It depends on the risk of the job, the stage and the contract. There is no universal percent.
Is contingency the same as an allowance?
No. An allowance is for a known item the client has not selected. A contingency covers unknown costs.
Who keeps unspent contingency?
The contract decides. On some cost-plus contracts the savings go to the owner or are shared.
Sources
- AIA, Document A102-2017 Cost of the Work Plus a Fee with a GMP, Sections 5.2 and 12.1.5 (sample)
- Buildertrend, Construction contingency guide for residential projects
- Procore, Construction cost reporting
Related guides
- Contingency tracking for custom home builders
- Allowance tracking for custom home builders
- Cost-plus open-book reporting for builders
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.