Notice of furnishing: definition and example
A plain definition for custom and spec home builders, with a worked example.
Definition: A notice of furnishing is a notice a Michigan subcontractor or supplier sends to the designee and general contractor named in the notice of commencement, within 20 days after first furnishing labor or material, to preserve construction lien rights. A contractor working directly for the owner does not need one.
Also called: Michigan notice to preserve lien rights
How it works for a home builder
Under MCL 570.1109, subcontractors and suppliers must serve the notice personally or by certified mail within 20 days after first furnishing labor or material. Laborers have separate deadlines tied to unpaid wages. A contractor who contracts directly with an owner does not need to send one to preserve lien rights.
A builder who is the general contractor should log every notice received, by sub, date and house, and match it to payments and waivers. A notice in the file means that sub expects to be paid before final payment on that house.
Example
Notice log, Lot 14. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Framing sub, first delivery March 3 | Notice received March 10 |
| Roofing supplier, first delivery April 2 | Notice received April 18 |
| Electrician, first work April 20 | No notice yet, deadline May 10 |
Made-up dates. A missing notice is tracked, not assumed.
Common questions
How long does a sub have to send a notice of furnishing in Michigan?
Within 20 days after furnishing the first labor or material, under MCL 570.1109, for subcontractors and suppliers.
Does the general contractor need to send one?
No. A contractor with a direct contract with the owner or lessee is not required to provide a notice of furnishing to preserve its lien rights.
Where should a builder keep notices of furnishing?
In the house file, next to the sworn statement and lien waivers, with the sub name, date received and amount.
Sources
- Michigan Compiled Laws 570.1109, notice of furnishing
- Michigan Compiled Laws 570.1108, notice of commencement
- Michigan Compiled Laws 570.1110, sworn statement by contractor or subcontractor
Related guides
- Michigan sworn statements and lien waivers for home builders
- Lien waivers for custom home builders
- Accounts payable workflow for home builders
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.