Short answer: In Michigan, a contractor must give the owner a sworn statement when payment is due or requested, or when the owner demands one. It lists every subcontractor, supplier and unpaid laborer, with contract price, amount paid and amount owing. A builder's books should produce those numbers by house. Lien waivers are separate: a partially paid claimant gives a partial unconditional waiver on request, and a fully paid one gives a full waiver.

What does Michigan require for a sworn statement and lien waivers?

Michigan law has a contractor give the owner a sworn statement when payment is due, when the contractor requests payment, or when the owner demands it. It identifies unpaid subcontractors, suppliers and laborers. A claimant who is fully paid gives a full unconditional waiver, and a partly paid claimant gives a partial unconditional waiver if asked.

DocumentWhen it is givenStatute
Sworn statementWhen payment is due or requested, or on the owner's demandMCL 570.1110
Full unconditional waiverAfter the claimant's contract is fully paidMCL 570.1115(2)
Partial unconditional waiverAfter partial payment, for the amount received, if the owner requests itMCL 570.1115(3)
Conditional waiver (partial or full)Effective when the amount stated is paidMCL 570.1115(4)
Residential owner relying on a waiverVerify a waiver not received directly from the claimant before relying on itMCL 570.1115(7)

General information from the statute text, not legal advice. Ask your attorney.

This is a bookkeeping guide, not legal advice. We are bookkeepers based in Rochester Hills, Michigan, not attorneys. The statutes below were read on the Michigan Legislature's site on November 17, 2026. Ask your attorney how they apply to your contract, and note that other states have their own rules and forms.

Two documents, two jobs

Michigan's Construction Lien Act (1980 PA 497) uses two documents that builders often mix up. The sworn statement is a notarized list of who you have hired on a house and what you owe each of them. A lien waiver is a signed release of lien rights by a sub or supplier for money received or about to be received. Your books feed the first one directly and prove the second.

DocumentWho gives itTo whomWhenStatute
Sworn statementContractorOwnerWhen payment is due or requested, or on the owner's demandMCL 570.1110(1)
Sworn statementSubcontractorContractorWhen payment is due to the sub or the sub requests itMCL 570.1110(3)
Sworn statementSubcontractorOwnerOn the owner's demandMCL 570.1110(2)
Partial unconditional waiverLien claimant paid in partOwner or designeeOn request, for the amount receivedMCL 570.1115(3)
Full unconditional waiverLien claimant paid in fullOwner or designeeOn full paymentMCL 570.1115(2)
Conditional waiverLien claimantOwner or designeeEffective once the stated amount is paidMCL 570.1115(4)

What the sworn statement lists

Under MCL 570.1110(4), the statement lists each subcontractor and supplier you have contracted with on the improvement, plus any laborers owed unpaid wages, fringe benefits or withholdings. For each name the statutory form has columns for the type of improvement furnished, total contract price, amount already paid, amount currently owing and an optional balance to complete. It is sworn before a notary, and the form warns that a false statement with intent to defraud carries criminal penalties.

The statute also says a contractor who has not provided the statement before recording a claim of lien is not entitled to payment, and cannot file to enforce the lien, until the statement is provided (MCL 570.1110(9)). In plain terms, the paperwork is part of getting paid.

Want sworn statement support built into your draw process? Request a Relationship Assessment.

Where each column comes from in your books

  • Name and type of improvement. The vendor and the cost code. A tidy vendor list and cost codes make this a report, not a hunt.
  • Total contract price. The signed subcontract or purchase order amount, including approved change orders. QuickBooks Online does not track this natively, which is why we keep committed costs in a purchase order or schedule by house.
  • Amount already paid. Bill payments to that vendor for that house, as of the statement date.
  • Amount currently owing. Open bills for that vendor and house, and any retainage payable you are holding.
  • Balance to complete. Contract price less billed to date. Optional on the form, but useful for your own cost-to-complete view.

If those columns do not agree with your job cost report, the sworn statement is the wrong place to find out. We reconcile the vendor-by-house totals before the statement is signed.

How lien waivers work in Michigan

MCL 570.1115 says nobody may require a lien waiver in advance of work performed as part of a contract, and a waiver obtained that way is invalid except to the extent payment was actually made. A claimant who receives full payment must give the owner a full unconditional waiver. A claimant who receives partial payment must give a partial unconditional waiver for the amount received if the owner or designee asks. Conditional waivers take effect when the stated amount is paid.

For a residential structure there is an extra rule. Where the claimant has filed a notice of furnishing, or is excused from filing one, the owner or designee may not rely on a waiver delivered by anyone other than the named claimant unless they first verify it with the claimant in writing, by telephone or in person (MCL 570.1115(7)). If you collect waivers for an owner, build that call or email into your routine and keep a note of it.

A waiver log that ties to payments

  1. List every sub and supplier on the house with the payment you are about to make.
  2. Collect a conditional waiver for the new payment, and an unconditional waiver for the prior payment that has cleared.
  3. Check each waiver's amount and through-date against the bill payments in your books.
  4. Mark any gap, such as a waiver that does not cover everything owed through the date shown, before you release funds.
  5. File the waiver and any verification note by house, so the next draw package can attach them.

Our broader guide on lien waivers for custom home builders covers the general approach. Use your attorney's forms for anything Michigan-specific.

Retainage and timing

MCL 570.1115(5) says retainage that is not payable until a certain event, beyond providing the improvement, is not due as of the date of the improvement. That is a legal point about when money is due. For the books, keep retainage in its own account by house so the sworn statement and your balance sheet agree.

How we help

Our team builds the vendor-by-house totals, keeps committed costs and retainage by house, and tracks waivers against each payment so your sworn statement numbers tie out. Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, construction bookkeeping, pricing or request a Relationship Assessment.

Sources

Common questions

When does a Michigan contractor have to give a sworn statement?

Under MCL 570.1110(1), when payment is due to the contractor from the owner, when the contractor requests payment, or when the owner demands one.

What does a Michigan sworn statement list?

Each subcontractor and supplier the contractor has contracted with, plus laborers owed unpaid wages or fringe benefits, with the contract price, amount paid and amount currently owing for each. It is signed before a notary.

Can an owner require a lien waiver before work is done in Michigan?

No. MCL 570.1115 says a person may not require, as part of a contract, that lien rights be waived in advance of work performed. A waiver obtained that way is invalid except for amounts actually paid.

What is the difference between a conditional and unconditional lien waiver?

A conditional waiver takes effect when the stated payment is made. An unconditional waiver does not depend on a later payment. Michigan requires a partially paid claimant to give a partial unconditional waiver for the amount received, if asked.

Can the books produce the sworn statement?

They should. Contract price, paid and owing by vendor and house come from committed costs, bill payments and open bills. We reconcile those totals to the job cost report before you sign.

Is this legal advice?

No. We are bookkeepers, not attorneys. Ask your attorney how Michigan's Construction Lien Act applies to your contracts.

What does Michigan require for a sworn statement and lien waivers?

Michigan law has a contractor give the owner a sworn statement when payment is due, when the contractor requests payment, or when the owner demands it. It identifies unpaid subcontractors, suppliers and laborers. A claimant who is fully paid gives a full unconditional waiver, and a partly paid claimant gives a partial unconditional waiver if asked.

Related

By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.

See where your margin goes, house by house.

Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.