Notice of commencement: definition and example
A plain definition for custom and spec home builders, with a worked example.
Definition: A notice of commencement is a form that, under Michigan's Construction Lien Act, the owner or lessee records with the county register of deeds before improvements begin. It names the property, the owner, the designee and the general contractor, and it starts the notice-of-furnishing process for subcontractors and suppliers.
Also called: Michigan construction lien notice
How it works for a home builder
The statute, MCL 570.1108, requires the owner or lessee who contracts for the improvements to record the notice before work starts. For residential structures, section 108a also requires the owner to complete and return a notice of commencement when a contractor, subcontractor, supplier or laborer requests one in writing.
For a builder, the notice matters because it names who receives notices of furnishing and where. Subs and suppliers send notices to the designee and general contractor at the address shown, so the builder needs a process to catch them. Other states use different filings, so check with your attorney.
Example
Where the notice fits. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Owner records notice of commencement | Before work starts |
| Framing sub first delivers lumber | March 3 |
| Sub's notice of furnishing due to the designee and general contractor | Within 20 days, by March 23 |
Made-up dates to show the order of events. This is not legal advice.
Common questions
Who records the notice of commencement in Michigan?
The owner or lessee contracting for the improvements records it with the register of deeds before the improvements begin.
Who receives notices of furnishing?
The designee and the general contractor named in the notice of commencement, at the address shown.
Do other states use a notice of commencement?
Many do, with different rules and forms. Ask a construction attorney in your state.
Sources
- Michigan Compiled Laws 570.1108, notice of commencement
- Michigan Compiled Laws 570.1109, notice of furnishing
- Szura & Delonis, Lien waivers in Michigan
Related guides
- Michigan sworn statements and lien waivers for home builders
- Lien waivers for custom home builders
- The construction loan draw process
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.