Guide

Designing a milestone draw schedule for a fixed-price build

How to split a contract into milestone payments that follow your costs, so you are not funding the house from your own account or billing so far ahead that an owner or lender pushes back.

Short answer: A milestone draw schedule splits the contract price into payments tied to stages of construction. Design it by estimating cumulative cost at each milestone, then setting cumulative billings close to that curve, with a modest allowance for the deposit and a holdback at the end. Compare cumulative billed to cumulative cost at every milestone. Persistent negative gaps mean you fund the build, and large positive gaps may draw owner or lender objections.

What a draw schedule is for

On a fixed-price contract the owner agrees to pay in stages. The schedule decides when your cash arrives relative to when your costs go out. A well-designed one keeps you close to cash neutral and gives the owner clear, verifiable stages. A poorly designed one leaves you carrying the build, or exposes you to a dispute about being paid ahead of the work.

Step 1: estimate cumulative cost by milestone

List your milestones and estimate cumulative cost at the end of each, from your budget by cost code. The numbers below are made up for a $1,000,000 contract with an $800,000 estimated cost, so the planned gross profit is $200,000 and the margin is 20 percent.

Want a draw schedule that matches your cash needs? Request a Relationship Assessment.

Step 2: set billings and compare to the cost curve

Schedule A, front-weighted

MilestoneBillCumulative billedCumulative cost (estimate)Cash position vs cost
Deposit at signing10%$100k$20k$80k ahead
Site work and foundation15%$250k$150k$100k ahead
Framing20%$450k$340k$110k ahead
Roof and rough-ins15%$600k$470k$130k ahead
Insulation and drywall10%$700k$580k$120k ahead
Cabinets and trim10%$800k$680k$120k ahead
Finishes10%$900k$770k$130k ahead
Final completion10%$1000k$800k$200k ahead

Schedule A keeps you $80,000 to $130,000 ahead of cost throughout. You are never funding the house, but the owner is funding it, and a lender or owner may question billing that far ahead of the work. Whether that is acceptable depends on your contract and on any rules that apply to deposits and payments where you build.

Schedule B, back-weighted

MilestoneBillCumulative billedCumulative cost (estimate)Cash position vs cost
Deposit at signing5%$50k$20k$30k ahead
Site work and foundation10%$150k$150keven
Framing15%$300k$340k$40k behind
Roof and rough-ins15%$450k$470k$20k behind
Insulation and drywall15%$600k$580k$20k ahead
Cabinets and trim15%$750k$680k$70k ahead
Finishes15%$900k$770k$130k ahead
Final completion10%$1000k$800k$200k ahead

Schedule B tracks cost more closely. It puts you as much as $40,000 behind at framing, which you fund from your own cash, and it ends the build with the same $200,000 profit. If your line of credit or working capital cannot carry that dip, you need a larger deposit or a smaller framing payment. The best schedule is the one whose largest negative gap you can comfortably fund.

Both schedules total 100 percent of the contract and both end with the same profit. What differs is when the cash arrives. Our free draw schedule template calculates draw amounts and retainage for your own split, and the WIP schedule example shows how the same billings appear as over or under billing.

Design rules that hold up

  1. Tie each draw to a visible stage the owner can verify, such as framing complete or roof dried in, not a date.
  2. Keep the deposit sensible. It covers early costs and signals commitment, but check your state and local rules on deposits before setting it.
  3. Hold back a meaningful final payment. It is your last leverage for punch list and close-out, and the owner's too.
  4. Decide how retainage works in both directions. If the owner holds retainage from you, or you hold it from subs, see retainage and customer deposits.
  5. Plan for change orders. Bill approved changes in the next draw or on their own line, and update the schedule so the percentages still total the new contract price. See change order tracking.
  6. Align with the lender's draws if the owner is financing. The owner's payment schedule and the lender's draw schedule differ. See lender draw budget vs job budget.

Booking it in QuickBooks Online

Intuit supports progress invoicing, where you create an estimate and then bill portions of it as work progresses. See our guide on progress invoicing in QuickBooks Online. Whatever method you use, keep the schedule, the invoices and the WIP schedule in agreement, so the draw package, the receivable and the margin all tell the same story.

This is a planning guide, not legal advice. Check your contract and your state's rules on deposits, retainage and payment.

How we help

Our team checks your draw schedule against your cost curve, prepares each draw package and keeps billings, retainage and WIP aligned. Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, construction bookkeeping, pricing or request a Relationship Assessment.

Sources

Common questions

How do you design a draw schedule for a fixed-price home?

Estimate cumulative cost at each milestone, set cumulative billings close to that curve with a deposit and a final holdback, and check the gap between cumulative billed and cumulative cost at each stage.

What is a normal draw schedule for a custom home?

There is no standard. It depends on your costs, contract, owner and lender. This page shows two illustrative schedules with made-up numbers and how to test them.

Should a builder bill ahead of the work?

A modest deposit is common, but billing far ahead of cost can draw owner or lender objections. Check your contract and local rules on deposits and payments.

What happens if my draw schedule is back-weighted?

You fund the build in the middle stages. Make sure your working capital or line of credit can carry the largest gap, or increase early payments.

How do change orders affect the draw schedule?

They change the contract price. Bill approved changes in the next draw or on their own line and update the schedule so percentages total the new price.

Is the owner's draw schedule the same as the lender's?

No. The owner's payment schedule to the builder and the lender's draw schedule to the borrower can differ and should be reconciled.

Related

By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.