Closing out a custom home in the books
Final billing, retainage, late bills, warranty and the last job cost review.
Short answer: Closing out a custom home means the books for that house are final: the last invoice and change orders are billed, retainage and deposits are cleared, every bill and final lien waiver is in, WIP entries are reversed to zero, and warranty costs have a home. Then mark the project complete and review final cost against budget.
Why closeout is its own step
Handing over the keys is not the end of the house in the books. Late trade bills arrive for weeks, retainage is still owed in one direction or both, and the customer deposit account may still hold money that should have been applied. If nobody closes the job on purpose, those leftovers sit on the balance sheet, the final margin keeps moving, and the next house's numbers get mixed in. A clean closeout gives you a final, trustworthy margin for the house and a short list of lessons for the next estimate.
The closeout checklist
1. Final billing
- Every approved change order has been invoiced. Compare your change order log to invoices on the project. See change order tracking.
- Allowances are trued up, with overages billed and credits issued. See allowance tracking.
- On cost-plus jobs, the final cost report and fee have been reconciled and billed.
- For a construction loan, the final draw has been requested with the documents the lender and title company need. See the draw package checklist.
2. Retainage and deposits
- Retainage receivable from the owner or lender is billed and collected, and retainage payable to trades is released once their work is accepted and their final waivers are in.
- The customer deposit liability for this house is zero. Any deposit not yet applied to an invoice gets applied or refunded. See retainage and customer deposits.
3. Every cost is in
- Open purchase orders are closed or matched to their final bills. See purchase orders and committed costs.
- Ask each trade and supplier for a final invoice. Known costs that have not been billed yet get accrued to the house so the margin does not change after you have reviewed it.
- Final unconditional lien waivers are collected against final payments. See lien waivers.
- Labor from the last payroll is posted to the house.
4. WIP goes to zero
If you keep monthly books on percentage of completion, the house's over or under billing should be zero once it is complete and fully billed. Revenue earned now equals the contract price plus change orders. A leftover balance means something was missed. See WIP over and under billing.
5. Warranty has a home
Decide where post-closing repairs go before the first call comes in. Many builders charge them to a warranty expense account or against a warranty reserve rather than reopening the house, so the final margin stays final. Our guide to builder risk and warranty reserves covers the setup. Buildertrend has a Warranty job status for this period, and its Warranty feature tracks claims and service appointments by job.
6. Close the job in the software
- QuickBooks Online. Projects can be set to In progress, Completed or Canceled. Intuit notes that marking a project completed clears it from the main Projects list, and you can still filter to see it. If late costs appear, you can set it back to In progress.
- Buildertrend. Job statuses are Pre-Sale, Open, Warranty and Closed. Buildertrend's help describes Closed as a job that has completed both the Open and Warranty stages, and closed jobs drop out of the default Jobs menu until you filter for them.
- Close the house's cost codes or budget in your job software so new bills cannot be coded to it by accident.
Want each house closed out cleanly, with final margin you can trust? Request a Relationship Assessment.
Closeout at a glance
| Area | Done when |
|---|---|
| Final billing | Every approved change order is invoiced, allowances are trued up and the final draw is requested |
| Retainage and deposits | Retainage is collected and released, and the customer deposit liability for the house is zero |
| Costs | Open purchase orders are closed, late bills are accrued and final unconditional waivers are in |
| WIP | Over or under billing for the house is zero |
| Warranty | Post-closing repairs have their own account |
| Software | The job is marked completed or closed and its cost codes are closed to new bills |
The final job cost review
Once the numbers are final, sit down with three columns by cost code: original budget, revised budget with change orders, and final actual. Look at where the house finished compared to where it started, which cost codes moved the most, how much margin came from change orders, and how long the house took compared to plan. Write the two or three lessons into your estimating template while they are fresh. Our job cost report guide walks through reading those columns.
How long it takes
The checklist itself is quick. The wait is for late bills, final waivers and retainage. A practical approach is to run the checklist at handover, set a follow-up date for the stragglers, and call the house closed once the last bill is in and warranty has its own account.
How we help
Our team runs this closeout on every house as part of the monthly close: final billing checks, retainage and deposits, late bill accruals, WIP reversal and a final budget vs actual by cost code. Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, construction bookkeeping, pricing or request a Relationship Assessment.
Sources
- Intuit, Create projects in QuickBooks Online
- QuickBooks Community, Reopening a project marked completed
- Buildertrend, Construction Job Management Guide (closing a job)
- Buildertrend, Warranty Management Overview
Common questions
When is a custom home closed in the books?
When it is fully billed, retainage and deposits are cleared, every known cost is in or accrued, WIP is zero and warranty costs go to their own account.
What if a bill arrives after I closed the job?
Post it to the house and note the change in the final review. If late bills keep showing up, accrue known costs at closeout and wait longer before calling it final.
Should warranty repairs reopen the job?
Usually not. Charge them to a warranty account or reserve so the house's final margin stays final, and track claims by house.
Does QuickBooks Online lose a completed project's data?
No. A completed project drops off the main Projects list but keeps its transactions, and you can filter to see it or set it back to In progress.
Can you handle closeout for us?
Yes. Our team runs closeout on each house as part of the monthly close, and our founder reviews it.
Related
- How to job cost a custom home
- Retainage and customer deposits
- Builder risk and warranty reserves
- How to read a job cost report
- Month-end close checklist
- Job costing
- Glossary: Warranty reserve
- Glossary: Substantial completion
- Request a Relationship Assessment
- Year-end close and CPA handoff checklist for home builders
By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.