Over billing vs under billing
What each term means and how they differ for a home builder.
Short answer: Over billing means a builder has billed more than it has earned on a house, so cash is ahead of the work, and it is a liability. Under billing means more work is done than billed, so billing is behind, and it is an asset. Both are billed to date minus earned revenue.
Side by side
| Over billing | Under billing | |
|---|---|---|
| Billed vs earned | Billed to date is more than earned revenue | Billed to date is less than earned revenue |
| Cash position | Cash is ahead of the work | The builder is funding the work |
| On the WIP schedule | Liability | Asset |
| Common causes | Front-loaded draws or deposits, stale cost to complete | Unbilled change orders, slow invoicing, draws not yet requested |
| Main risk | Cash spent elsewhere, short at the end of the house | Work that may never be billed or collected |
| First fix | Reserve the cash for the house | Bill the work and approved changes |
Example
Two houses, one month. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Lot 14: earned $300,000, billed $340,000 | Over billed $40,000 |
| Lot 9: earned $297,600, billed $270,000 | Under billed $27,600 |
| Net across both houses | Over billed $12,400 |
Made-up numbers. Netting hides the difference, so a WIP schedule shows each house.
Common questions
Which is worse, over billing or under billing?
Neither is automatically bad. Over billing becomes a risk when the cash is spent elsewhere. Under billing becomes a risk when work is never billed or collected.
How do I calculate it?
Billed to date minus earned revenue. Earned revenue is contract price times percent complete.
Sources
- CFMA, WIP accounting: critical and often misunderstood
- Sage, What does your monthly WIP and forecasting meeting look like?
- 26 U.S. Code Section 460, long-term contracts (Cornell LII)
Related guides
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.