Over billing: definition and example
A plain definition for custom and spec home builders, with a worked example.
Definition: Over billing means a builder has billed a client more than the revenue earned to date based on percent complete. Cash is ahead of the work. It is a liability on the WIP schedule, because that cash is needed to finish the house, and it can hide a margin problem.
Also called: billings in excess of costs and estimated earnings
How it works for a home builder
Over billing is not automatically bad. Front-loaded draws or deposits create it, and it helps cash flow. The risk is spending that cash on other houses or overhead, then running short when the costs arrive.
Over billing is calculated as billed to date minus earned revenue. If the estimated total cost is stale, the percent complete is wrong, and the over billing figure is wrong with it.
Example
Over billing on Lot 14. All numbers below are made up for illustration. They are not a real client or house.
| Item | Amount |
|---|---|
| Earned revenue (55.6% of $540,000) | $300,000 |
| Billed to date | $340,000 |
| Over billing | $40,000 |
Made-up numbers. The $40,000 is cash collected for work not yet done.
Common questions
Is over billing a problem?
Not by itself. It becomes a problem if the cash is spent elsewhere and not reserved to finish the house.
How is over billing shown in the books?
As a liability, often called billings in excess of costs and estimated earnings, on the balance sheet under the percentage-of-completion method.
Why do lenders care about over billing?
It shows whether billings are ahead of the work and whether the builder has the cash to finish.
Sources
- CFMA, WIP accounting: critical and often misunderstood
- 26 U.S. Code Section 460, long-term contracts (Cornell LII)
- Sage, What does your monthly WIP and forecasting meeting look like?
Related guides
Related terms
Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.
By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.