Equipment and truck costs in builder job costing
Rented equipment is easy. The skid steer you own, the dump trailer and the super's pickup are where job costs go missing. Here is how to charge them to the right house.
Short answer: Put rented equipment straight on the house and cost code from the rental bill. For equipment you own, set an internal rate per hour or day that charges each house for its use and credits an equipment recovery account. Trucks shared across jobs usually stay in overhead or general conditions unless you track their use by house.
Not sure your houses carry their full equipment cost? Our team can check. Request a Relationship Assessment.
Three kinds of equipment cost
| Type | Examples | Where it usually goes |
|---|---|---|
| Rented from a third party | Lift, excavator, dumpster, fencing, portable toilet | Straight to the house and cost code on the bill |
| Owned equipment used on houses | Skid steer, mini excavator, dump trailer, scaffolding | Charged to houses at an internal rate; actual costs sit in an equipment account |
| Company trucks and small tools | Superintendent pickup, shared tools, consumables | Overhead or project general conditions, unless use is tracked by house |
Rented equipment: code it on the bill
A rental bill is a direct cost. Enter it against the customer or project in QuickBooks Online, or in Buildertrend or JobTread so it syncs, with your equipment rental cost code. Delivery, pickup, fuel surcharges and damage waivers on the same bill go to the same house. When one rental serves two houses, split the bill by days on each, and note the split on the bill so the monthly tie-out makes sense later.
Owned equipment: why it needs a rate
When you own the machine, there is no bill per house. Depreciation, loan interest, insurance, registration, fuel and repairs all land in general accounts, and none of it reaches a house unless you put it there. A CFMA forum article on internal equipment costs puts it simply: the goal is to cost all equipment as a direct cost, and if you do not, it becomes overhead.
That matters for a builder because two houses built with the same skid steer can show very different margins if one rented and one used yours "for free." It also hides whether owning the machine is cheaper than renting.
How to build an internal rate
An article in Construction Equipment describes the rate as covering ownership costs (depreciation, finance charges, licenses, insurance and property taxes) plus operating costs (fuel, repairs and wear), averaged over the machine's life. It also stresses using the same rate in your estimate and your job costs, so a variance means the crew used more or less equipment, not that the rate changed.
SAMPLE (made-up numbers): a skid steer has $14,000 a year of ownership cost and $6,000 a year of operating cost. You expect it to be on houses 500 hours a year. The rate is $20,000 divided by 500, or $40 an hour. A house that used it 30 hours carries $1,200 of equipment cost.
The CFMA forum article describes three ways to charge it: a single hourly rate, a working rate plus a lower idle rate for time parked on site, or a daily, weekly or monthly "rent" whenever it sits on the job. The rent approach stops a machine from sitting on one house for convenience while only a few hours get charged. Pick one method and use it on every house.
Utilization drives the rate. A CFMA Orange County chapter article gives an example of a machine whose rate assumed 1,200 hours a year at $100 an hour of ownership cost; if it actually runs 1,800 hours, the true ownership cost is closer to $67 an hour, and jobs get overcharged. For a builder, the risk usually runs the other way: fewer hours than planned, so the rate under-recovers.
Recording it in QuickBooks Online
- Keep actual equipment costs together. Use an equipment section in the chart of accounts for depreciation, insurance, fuel and repairs.
- Post the monthly charge by house. A journal entry debits your job cost equipment account with each house in the Name column and credits an equipment cost recovery account that sits next to the actual costs.
- Know the limits. Journal entry lines carry an account, description, name, class and location, but not a product or service. If your cost codes live in products and services, the charge reaches the house but not the cost code, so give equipment its own account or post the charge on the budget in Buildertrend or JobTread. In a QuickBooks Community thread, Intuit staff said project journal entries appear on the project's Transactions tab while the Overview page shows account totals, so check how your project reports show them.
- Read the net. Actual equipment costs less recovery is your under- or over-recovery. A large balance means the rate or the hours are off.
Depreciation in your books for this purpose and depreciation on your tax return can differ. Your CPA decides the tax side. We do not give tax advice.
Company trucks and small tools
A superintendent's pickup serves every house that superintendent runs. Most builders keep truck costs in overhead and recover them through the overhead rate, or treat them as project general conditions and spread them by house. See shared job costs and general conditions for allocation methods. A truck dedicated to one long build can be charged to that house at a daily rate, the same way as other owned equipment. Small tools and consumables are usually overhead because tracking them by house costs more than it tells you.
If the equipment sits in a separate LLC that rents to your building company, the rent is a real bill to the house plus an intercompany entry. See multi-entity job costing.
A monthly true-up
- Compare equipment recovery charged to houses with actual equipment costs for the month and the year to date.
- Review hours or days per machine. Low use is a signal to rent instead.
- Reset the rate at least once a year, and when a machine is bought or sold.
- Compare each internal rate with what a rental yard charges. The CFMA forum article warns that charging a job more than renting would cost means you own the wrong equipment, too much of it, or the costing method is not working.
How we help
Our team sets up equipment accounts and internal rates with you, posts equipment charges to each house monthly and shows the recovery against actual cost. Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, construction bookkeeping, pricing or request a Relationship Assessment.
Sources
- CFMA forum, Internal Equipment Costs (hourly, idle and rental-style charging; costing equipment as direct cost)
- Construction Equipment, Three Roles for the Rate (ownership and operating costs; same rate for estimating and job costing)
- CFMA Orange County, 2 Things Every Heavy Civil CFO Must Nail: Equipment Rates and Capital Decisions (utilization example)
- QuickBooks Community, Is there a way while entering a journal to assign an expense to a project? (Intuit staff replies)
Common questions
Should equipment rental be a job cost?
Yes. Rental from a third party is a direct cost of the house that used it, including delivery, fuel and damage waiver charges on the same bill.
How do I charge owned equipment to a job?
Set an internal rate per hour or day that covers ownership and operating costs, charge each house for the time it used the machine, and credit an equipment recovery account.
What goes into an internal equipment rate?
Ownership costs such as depreciation, financing, insurance and registration, plus operating costs such as fuel and repairs, divided by the hours or days you expect to use it.
Are pickup trucks a job cost or overhead?
Usually overhead or project general conditions, since one truck serves several houses. A truck dedicated to one build can be charged to it at a daily rate.
Can I post equipment charges to a project with a journal entry in QuickBooks Online?
Yes, by putting the project in the Name column. Journal entry lines do not carry a product or service, so plan how the charge reaches your cost codes.
Can you set up equipment costing for us?
Yes. We set the accounts and rates with you, post the charges by house monthly and report recovery against actual cost.
Related
- How to job cost a custom home
- Overhead allocation and overhead rate
- Shared job costs and general conditions
- Labor burden in builder job costing
- Cost codes for custom home builders
- Multi-entity job costing
- Glossary: direct vs indirect costs
- Job costing service
By John Mos, Founder. Updated . We do not give tax or legal advice. Please ask your CPA or attorney.
See where your margin goes, house by house.
Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.