WIP schedule vs job cost report

What each term means and how they differ for a home builder.

Short answer: A job cost report gives detail for one house by cost code against budget. A WIP schedule summarizes every open house on one line, adding percent complete, earned revenue, billings and over or under billing. The WIP schedule is built from the job cost report.

Side by side

WIP scheduleJob cost report
Level of detailOne line per houseCost codes within one house
Key columnsContract price, estimated total cost, percent complete, earned revenue, billed, over or underBudget, actual, committed, variance, forecast
Main questionIs billing ahead of or behind the work?Which costs are over budget?
Who asks for itLenders, sureties, CPAsOwner, project manager
FrequencyMonthly after closeMonthly or more often

Example

Lot 14. All numbers below are made up for illustration. They are not a real client or house.

ItemAmount
Job cost report: framing$9,400 over budget
WIP schedule: Lot 1455.6% complete, over billed $40,000

Made-up numbers.

Common questions

Which comes first?

The job cost report. The WIP schedule uses its cost to date and cost to complete.

Can a house be fine on one and not the other?

Yes. It can be on budget and still over billed, which strains cash.

Sources

Related guides

Related terms

Want your own houses run this way? Our founder reviews every close. We quote a flat monthly price for each builder, starting at $1,500 a month, with typical engagements between $2,500 and $8,500 a month. Start with a $1,500 Margin Review for written findings. See job costing, pricing or request a Relationship Assessment.

By John Mos, Founder. Updated . Definitions are general information. We do not give tax or legal advice. Please ask your CPA or attorney.

See where your margin goes, house by house.

Tell us about your homes and your books. If we are a fit, we start with a $1,500 Margin Review: written findings and a fixed quote in 10 business days, credited to your onboarding fee if you sign up.